In 23rd April, 2017, a section of R2 route- from R2 Embankment to Nguyen Co Thach Street- was put into use by the Department of Transportation. Regarding the upcoming opening routes, Dai Quang Minh has finished constructing several bridges, including Bridge No.10, Bridge No.15, viaduct No.1, viaduct No.2, R2 Embankment; along with the section of R2 road that extends from Nguyễn Cơ Thạch Street to C4 Intersection; the section of R3 road that extends from Mai Chi Tho Street to C4 Intersection; and the section of R4 road that extends from C4 Intersection to Mai Chi Tho Street.
As to the remaining stretches of roads, Dai Quang Minh Corp. has completed the first layer of asphalt concrete, tree planting and lighting system installation. However, it is necessary to wait for some of the site clearance’s issues to be resolved.
Road R1 - From C4 Intersection to Bridge No.14
Road R2 - From Bridge No. 15 to C4 Intersection
Road R2 - From Bridge No.15 to C6 Intersection
Road R2 - Traffic clearance from Embankment R2 to C24 Intersection
Road R3 - From Bridge 17 to Mai Chi Tho Street
Road R4 - From C4 Intersection to Viaduct No.1
Road R4 - Viaduct No.2
Thu Thiem 2 Bridge Project
Currently, Thu Thiem 2 Bridge Project is entering the phase of land-grading and gathering equipment for soft soil treatment (Deep Soil Mixing Columns) for the access road leading to District 2.
Access road to Thu Thiem 2 Bridge – Land grading, gathering and installation of DSMC equipment.